Industrial Facilities and Investments
İzgaz , has completed 98% of its investments within the license boundaries of Kocaeli. Izgaz has realized the production of 3.015.038 meters of distribution and service line since 1994 to today.

                                   Products Concluded (September Year 2009)
PE MAIN LINE 1.946.386,5 m.
SERVICE LINE 758.672,1 m.
SERVICE BOX 81.381 pieces
STEEL TRANSFER        LINE 309.980 m.

Our currently continuing investments:
  • STEEL, PE AND SERVICE LINE CONSTRUCTION WORK ( 2009-2 )
  • CONTRACTING COMPANY: SÖNMEZ İNŞAAT
  • TERM OF TENDER: 90 DAYS
  • DATE WORK COMPLETED : NOVEMBER 7 2009
  • WORK TO BE CONCLUDED:
    • 120 Pieces Service Boxes
    • 1200 m. Service Lines
    • 9000 m. Distribution Lines
    • 2150 m. Steel Lines
    • 1 Piece Regional Regulator
POTENTIAL SUBSCRIBERS: 3247
  • SERVICE BOX PRODUCTION WORK - 2 ( 2009-3)
  • CONTRACTING COMPANY: BÖLENLER İNŞAAT
  • TERM OF TENDER: 120 DAYS
  • DATE WORK COMPLETED: DECEMBER 21, 2009
  • WORK TO BE CONCLUDED:
    • 500 Pieces Service Box
    • 6000 m. Service Line
    • Tender Cost : 128.250,00 TL
POTENTIAL SUBSCRIBERS: 1100

  2010 2011 2012 2013 2014 2015
STEEL, m.  2.500  0  8.500  0  0  0
PE, m.  50.500  50.000 55.000  55.000  50.000  50.000
SERVICE BOX, piece  3.370  2.500  2.500  2.700  2.500  2.000
SERVICE LINE, m.  35.500  30.000  30.000  32.400  32.500  24.000
REGIONAL REG. Piece  1  0  1  0  0  0
RMS_A STAT. Piece  0  0  1  1  0  0
VALVE ROOM, Piece
 0  0  5  0  0  0
SPECIAL PASS., m.  150 150  850 150 150 150